Safe harbor for renewable energy credits extended

RFP
Tax Hot Topics newsletter The IRS has issued guidance (Notice 2021-41) again extending the safe harbor deadlines for establishing that construction has begun and is continuous for the Section 45 renewable electricity production tax credit (PTC) and the Section 48 energy investment tax credit (ITC).

The notice provides that the continuity safe harbor is satisfied for projects that began construction in 2016 through 2019 if the project is placed in service within six calendar years of the year in which construction began. Projects started in 2020 are allowed five calendar years. Previous guidance (Notice 2021-05) allows 10 years for projects offshore or on federal land.

The PTC and ITC were extended under the Consolidated Appropriations Act in December. Construction on qualified PTC projects must now generally begin before Jan. 1, 2022, and taxpayers can elect to claim the ITC in lieu of the PTC for project that began construction by this date. The credit for wind under the PTC and ITC is reduced by 40% for construction beginning in 2021. The full 30% credit for solar property under Section 48 is only available for construction that began by the end of 2019. The credit is reduced to 26% for construction beginning by the end of 2022 and 22% for construction beginning in 2023.

IRS guidance generally allows taxpayers to establish that construction has begun by either satisfying a test showing “physical work of a significant nature” has begun or by incurring 5% or more of the total cost of the facility under a safe harbor. Both require taxpayers to make continual progress toward completion once construction is considered to have begun. In addition to the relief from the continuity safe harbor, Notice 2021-41 provides information harmonizing the continuity requirement under the physical work test and the 5% safe harbor.

Taxpayers who don’t use the continuity safe harbor that was extended by Notice 2021-14 must generally use a facts-and-circumstances analysis to determine if construction is continual. The following disruptions are excusable:

  • Severe weather conditions
  • Natural disasters
  • Certain licensing and permitting delays
  • Delays at the written request of government for safety, security or similar concerns
  • Transmission interconnection issues
  • Labor stoppages
  • Supply shortages
  • Delays in manufacturing custom components
  • Inability to obtain specialized equipment
  • Financing delays
  • The presence of endangered species

In addition, the following preliminary activities continue to be disqualified as physical work of a significant nature:

  • Planning or designing
  • Securing financing
  • Exploring
  • Researching
  • Conducting geologic mapping and modeling
  • Obtaining permits and licenses
  • Conducting geophysical, gravity, magnetic, seismic and resistivity surveys
  • Conducing environmental and engineering studies
  • Performing activities to develop a geothermal deposit prior to discovery
  • Clearing a site
  • Test drilling of a geothermal deposit
  • Test drilling to determine soil condition
  • Excavation to change the contour of the land (as distinguished from excavation for footings and foundations)
  • Removing existing turbines, towers, panels or other components

The IRS has indicated it will not issue private letter rulings or determination letters regarding the application of Notice 2021-41, prior IRS notices or the PTC and ITC beginning of construction requirement.

Contact:
Dustin Stamper
Managing Director
Washington National Tax Office
T +1 202 861 4144

Tax professional standards statement
This content supports Grant Thornton LLP’s marketing of professional services and is not written tax advice directed at the particular facts and circumstances of any person. If you are interested in the topics presented herein, we encourage you to contact us or an independent tax professional to discuss their potential application to your particular situation. Nothing herein shall be construed as imposing a limitation on any person from disclosing the tax treatment or tax structure of any matter addressed herein. To the extent this content may be considered to contain written tax advice, any written advice contained in, forwarded with or attached to this content is not intended by Grant Thornton LLP to be used, and cannot be used, by any person for the purpose of avoiding penalties that may be imposed under the Internal Revenue Code.

The information contained herein is general in nature and is based on authorities that are subject to change. It is not, and should not be construed as, accounting, legal or tax advice provided by Grant Thornton LLP to the reader. This material may not be applicable to, or suitable for, the reader’s specific circumstances or needs and may require consideration of tax and nontax factors not described herein. Contact Grant Thornton LLP or other tax professionals prior to taking any action based upon this information. Changes in tax laws or other factors could affect, on a prospective or retroactive basis, the information contained herein; Grant Thornton LLP assumes no obligation to inform the reader of any such changes. All references to “Section,” “Sec.,” or “§” refer to the Internal Revenue Code of 1986, as amended.